Technology leap with A+W software at GVG Deggendorf

Technology leap at GVG Deggendorf | A+W
Photo source
A+W Software

Date: 28 September 2021

Networked, digital, more efficient

Any glass finisher and manufacturer of safety glass on an industrial scale who can score points with high capacity, state-of-the-art production technology, and sophisticated service is a sought-after market partner. The glass processor Deggendorf mbH (GVG) is such an operation. It recently upgraded and installed the latest generation of A+W software, taking another step toward glass production 4.0.

GVG Deggendorf, which was recently purchased by Arbonia Deutschland GmbH, is a manufacturer of safety glass in southern Germany. Here, approximately 160 extremely well-trained employees use a state-of-the-art machine park to produce glass, many types even with tempered glass in the LAMI, and production runs around the clock. Each day, approximately 3000 square meters of TG are produced in two modern furnaces. Quality and on-time delivery are a matter of course, delivery times are reliably short. Thus it is no wonder that GVG Deggendorf is a long-standing partner of well-known premium suppliers, especially in the sanitary facilities and glass sectors. This is why the Deggendorf glass finishers are recording strong growth.

Becoming a 'smart factory' with new software

So that things remain this way and can be optimized further, it is necessary to constantly update the production technology and the software that controls it. Thanks to intelligent networking, all areas of the company are being integrated on the way to becoming a digital company.

That’s why last year, as part of a big project in cooperation with the software partner A+W, all of the software at GVG Deggendorf was updated and expanded. This was a challenging project that was implemented by a team of employees from both companies with great commitment and maximum expertise. Careful preparation, enough time, and especially the trusting and collegial climate on the team were critical factors for the successful implementation.

Proud of the successful project implementation – from left: Markus Wellisch, Production Manager and Project Manager for GVG Deggendorf; Andreas Fink, Managing Director GVG Deggendorf; Sebastian Dick, Project Manager A+W; Andreas Stern, Manager of Inside Sales for GVG Deggendorf.
Proud of the successful project implementation – from left: Markus Wellisch, Production Manager and Project Manager for GVG Deggendorf; Andreas Fink, Managing Director GVG Deggendorf; Sebastian Dick, Project Manager A+W; Andreas Stern, Manager of Inside Sales for GVG Deggendorf.

“We always had the feeling,” explains Markus Wellisch, Project Manager for GVG Deggendorf, “that A+W helped us quickly and expertly even when problems arose, so that we arrived at a good solution in the end. This creates trust, and I would do it this way again anytime”!

Live operation began at the start of 2021. GVG Managing Director Andreas Fink, “I am happy and proud that we kept on producing after the go-live; without production downtime, breakdowns or customer complaints. This was a big accomplishment for all participants”!

Production Terminals instead of paper in the clean room: production sequence and lite structure are displayed quickly and reliably.
Production Terminals instead of paper in the clean room: production sequence and
lite structure are displayed quickly and reliably.

What has changed at GVG Derggendorf due to the A+W software?

OK, almost everything. With the older software, it was no longer possible to manage today’s requirements for performance, transparency, and digital, paperless process control.

Today, the company is controlled in integrated fashion by the current ERP solution A+W Enterprise in the office and A+W Production in production. All information is available in real time exactly where it is needed.

The customer’s production data transmitted online is sent from A+W Enterprise directly to production, where, thanks to intelligent A+W interfaces, it is available immediately for control of the CNC machines: time-consuming manual machine programming is no longer required, which increases throughput speed immensely. No one has to carry around production papers or sketches, and potentially even multiple copies of these.

The vertical Systron grinding machine enables quick processing of rectangular lites.
The vertical Systron grinding machine enables quick processing of rectangular lites.

With the production planning module A+W Production, the lites are pre-sorted in cutting and fed into the appropriate processing stations. For this, orders are pulled apart, the lites are steered individually according to technical issues (e.g. glass thicknesses for tempering) through production, andreassembled again in shipping – without any errors or bottlenecks.

For the greatest flexibility in cutting and custom-tailored batches, GVG Deggendorf uses the A+W Realtime Optimizer on the cutting tables. With this application, already-planned optimization batches can be changed, combined or exchanged. For maximum utilization of the realtime optimization, the lables are printed directly in cutting only just before cutting begins. Changes to the cutting sequence are possible when handling rush orders and almost up to the start of production, for example. A+W Production Terminals at each workstation visualize all necessary lite and production data.

The A+W Smart Companion always knows where each lite is

A continuous PDC system based on the intelligent scan app A+W Smart Companion ensures that the status of each lite is always known: lites are scanned at each workstation, the scanners are read out via WLAN. And A+W Smart Companion is also used to control the automatic breakage pool.

The Benteler double-sider is equipped with two drills incl. milling and water cutting, and two outputs. The drills are run in parallel; that is, the lites can overtake one another. This is how bottlenecks during drilling are avoided.
The Benteler double-sider is equipped with two drills incl. milling and water cutting, and two outputs. The drills are run in parallel; that is, the lites can overtake one another. This is how bottlenecks during drilling are avoided.

Defective lites can be remade quickly this way, so that they can generally still be delivered on the promised date. “The handling of remakes,” explains Markus Wellisch, “is worlds better as compared to before”.

Andreas Fink adds: “With the new integrated solution, we have a technological basis for increasing our productivity and being able to deploy state-of-the-art machine technology more efficiently. Even now, we are much more productive as compared to 2020. With this important project, we worked with A+W to make our company fit for the digital future”.

Each lite is scanned at each workstation. This enables continuous lite tracing, maximum transparency, and prompt customer information about production status. And much more ...
Each lite is scanned at each workstation. This enables continuous lite tracing, maximum transparency, and prompt customer information about production status. And much more ...
600450 Technology leap with A+W software at GVG Deggendorf glassonweb.com

Others also read

The Sustainability Manager across the ASSA ABLOY EMEIA division, Leandro Peraro, will take his place on the sustainability debate panel at Glazing Summit 2021.
Online the video of the new Glass Unloader Art. GU by Forel. This new solution, presented for the first time in 2021 at GlassBuild America and at Vitrum is compatible with every kind of IG line.
Climate protection with windows
Navigating the regulation minefield is high on the agenda at this year’s Glazing Summit, which takes place on Thursday, October 21 at Edgbaston Stadium and Conference Centre, Birmingham.
The last 18 months has seen the biggest ever challenges in the window, door, and conservatory industry with the impact of Brexit and the Pandemic.
Your glass industry peers had a lot to say about the show, here’s some of the feedback we received.
The strain on installers due to pressure on the supply chain, record levels of demand, rising costs, and a worsening skills shortage, will take centre stage at the Glazing Summit.
Get an insight into the industry at WDMA's Executive Management Conference this October. Walk away with a pulse on the business and unique insights into the future of windows, doors, and skylights.
The Window & Door Manufacturers Association has released the WDMA 2021 U.S. Market Study for Window & Patio Door, Architectural and Entry Doors.
The Glazing Executives Forum, now in its 15th year, is organized by the National Glass Association and held in conjunction with GlassBuild America.
From Glass to Windows Seamlessly with A+W Clarity & A+W Cantor
All speakers for the Glazing Summit 2021 have now been confirmed by organisers – and the stellar line-up is a mouth-watering one.

Add new comment

From industry

Am Pfahlgraben 4
35415 Pohlheim
Germany

Polígono Lalín 2000
36512 Lalín Pontevedra
Spain

Ctra. Estación Km. 15.8
44415 Rubielos de Mora Teruel
Spain