HORN® ignites 400 t/d G2 furnace at GCA

HORN® ignites 400 t/d G2 furnace at GCA
Photo source
www.hornglass.com

Date: 5 March 2021

HORN® has started the furnace heat-up process at GCA's new 400 t/d end fired furnace in Turkey.

The lighting took place on Tuesday, 2 February. The first glass was on 19 February. The entire start-up process had been and will continue to be supported by HORN® technicians. This project is a very special one since we have installed our new forehearth system GCS® 301-advanced for the first time. The performance test is expected to begin in mid March.

Find out more about the new forehearth GCS® series 301-advanced:

FOREHEARTH GCS®  SERIES 301-ADVANCED

HORN® ignites 400 t/d G2 furnace at GCA

HORN® ignites 400 t/d G2 furnace at GCA

HORN® ignites 400 t/d G2 furnace at GCA

600450 HORN® ignites 400 t/d G2 furnace at GCA glassonweb.com

Others also read

Registration is now open for the 2026 Furnace Solutions Conference, organised by the Society of Glass Technology, which returns to St Helens, UK, on 3–4 June 2026.
Şişecam has successfully commissioned the new coated glass line at its San Giorgio di Nogaro plant in Northern Italy, an investment realized with 25 million Euro.
The LiTROS glass cutting line is a sophisticated, modular solution for industrial processing of float glass.
The new line, with an annual capacity of 6 million square meters, will operate alongside the existing coated glass line.
HORN Glass Industries delivers industry-leading float tin bath solutions designed for precision, quality and long-term performance.
Glass for Europe has stepped into the spotlight to ensure that advanced glazing technologies are fully recognised as strategic materials in Europe’s upcoming Advanced Materials Act.

Add new comment

From industry

İçmeler Mah. D-100 Karayolu Cad. No:44A,
34947 Tuzla,/İstanbul
Turkey

13 Beaufort Square
London
NW9 4FJ
United Kingdom

NEWS RELATED PRODUCTS

A+W Software GmbH
Thermoseal Group Ltd.
A+W Software GmbH
Glas Trösch Holding AG