New glass transforms one of the world’s busiest arenas | AGI Case Study

Rabinowitz Glass added the new upper band of curtain wall; photo © Joe Garvin except where noted
Photo source
Rabinowitz Glass added the new upper band of curtain wall | Photo © Joe Garvin
SCI Architects of New York, N.Y., was engaged to design the renovations. AGI member contractor Paul Rabinowitz Glass Co., Inc. of Philadelphia, Pa., performed the glazing scope through two phases of work from 2016-2018.

 

INTRODUCTION

Sports fans are well-acquainted with the Wells Fargo Center, one of the world’s busiest sports and entertainment arenas. The Philadelphia Flyers of the National Hockey League, Philadelphia 76ers of the National Basketball Association, Philadelphia Soul of the Arena Football League, and Philadelphia Wings of the National Lacrosse League all call the building home. The Wells Fargo Center also plays host to countless concerts and special events each year.

New curtain wall being cut into the facade (photo courtesy of Rabinowitz Glass)
New curtain wall being cut into the facade (photo courtesy of Rabinowitz Glass)

Opened in 1996, the Wells Fargo Center marked its 20th anniversary with a $250 million multi-year renovation. Owner Comcast Spectacor embarked on the ambitious project to transform the suite and mezzanine levels, add open-concept spaces, and provide refreshed patron amenities.

SCI Architects of New York, N.Y., was engaged to design the renovations. AGI member contractor Paul Rabinowitz Glass Co., Inc. of Philadelphia, Pa., performed the glazing scope through two phases of work from 2016-2018.

 

NEW CURTAIN WALL

The extensive glazing scope began on the building exterior, where two new runs of curtain wall were cut into the existing north and south façades to offer expansive views of the Philadelphia skyline. The new glass runs parallel to existing glazing, and the vertical mullions in both old and new sections needed to line up.

Straightforward in concept, in actuality, this alignment was challenged by the building’s geometry. The Wells Fargo Center is slightly conical, with framing that angles outward. All of the vertical mullions are segmented or angled toward the middle.

After curtain wall installation
After curtain wall installation (photo © Joe Garvin)

According to Rabinowitz Glass Project Manager Derek Erfurt, the building underwent a 3D laser scan before his team used AutoCAD and Rhino modeling software to understand the complex geometry. “We have some excellent drafters who were able to do intense 3D modeling of the system,” Erfurt explained. “They drew all of the curtain wall in 3D, which added a layer of difficulty to the fabrication process.”

 

CURTAIN WALL CHALLENGES

Cutting a new run of curtain wall into an existing building presented additional challenges. Selective demolition was required to understand the interior structure and determine how the new curtain wall could be anchored to the building. The original glass type was unavailable, so selective color matching was required to ensure the new and existing curtain wall glass would match. J.E. Berkowitz provided the final selection, installed within YKK’s YCW 750 SSG curtain wall system.

“One of the biggest challenges during window construction was maintaining temperature and humidity inside the building, especially after ice went down for hockey season in September,” explained Construction Project Manager Geoff Brock of Structuretone. “Before the existing metal panels were removed, we built temporary walls with tarps just inside the building, so that work could progress on the exterior without impacting interior conditioning.”

Interior showing skyline views and new concessions
Interior showing skyline views and new concessions (photo © Joe Garvin)

 

CONCESSIONS

In addition to the new curtain wall, Rabinowitz Glass installed decorative glass fronts on all of the concession stands on Levels 5 and 6. The white back-painted glass was ordered from Canada, with all pieces ordered based on “hold sizes.”

According to Erfurt, the tight schedule meant the millwork for the 20+ concession stands wouldn’t be available until just before the glass needed to be installed. This prevented simply measuring and ordering. Instead, all glass was ordered based on the millwork shop drawings. “It was almost like putting a puzzle together,” he said. “Little to no tolerance with the glass meant they had to have the millwork pieces perfect. Overall, it was successful.”

 

GUARDRAILS & MORE

New glass guardrails were installed at each of the ADA platforms that accommodate wheelchair seating throughout the arena. Rabinowitz Glass used heavy aluminum base with tempered laminated glass railings. Installation was phased over the summer months when numerous concerts took place, ensuring better viewing spots were completed sooner. New bathroom mirrors rounded out the comprehensive glazing project.

New ADA guardrail glass
New ADA guardrail glass (photo © Joe Garvin)

 

BEAT THE BUZZER

Just as athletes can’t change their game clock, the project team was driven by the inflexible basketball and hockey schedules. “You couldn’t just push back the home opener of the Flyers,” Erfurt said with a laugh. Construction manager, Structuretone, and all of the trades cooperated and all work was completed on schedule for a dramatically refreshed venue.

 

AGI Glazier
Paul Rabinowitz Glass Co., Inc.
Philadelphia, Pa.

Team
Owner: Comcast Spectacor | Phila.
Owner’s Rep: JLL | Philadelphia
GC: Structuretone | Philadelphia
Architect: SCI Architects | New York

Scope
New curtainwall; decorative glass
concession fronts; glass ADA
guardrails; bathroom mirrors

Completion
October 2018

600450 New glass transforms one of the world’s busiest arenas | AGI Case Study glassonweb.com

Others also read

Those at the 2020 Fenestration and Glazing Industry Alliance (FGIA) Annual Conference heard an economics expert offer perspective on several crucial, global topics.
The new halls C5 and C6 prompted a major re-shuffle of the sections at BAU in 2019, so adaptations for BAU 2021 are only moderate in scale.
Located on the Elbe River, on the western tip of the HafenCity in Hamburg, Germany, the Elbphilharmonie is one of the largest and most acoustically advanced concert halls in the world and an outstanding example of modern architecture.
Notification of Extension of Service Deadline for the 31st China International Glass Industrial Technical Exhibition (China Glass 2020)
The keynote speaker at the 2020 Fenestration and Glazing Industry Alliance (FGIA) Annual Conference made a case for servant leadership over traditional management.
The Fenestration and Glazing Industry Alliance (FGIA) recognized the contributions and achievements of its members and congratulated award winners at the inaugural FGIA Annual Conference Awards Banquet held Tuesday night in Ft. Lauderdale, Florida.

From industry

10924 Granite Street, Suite 200
Charlotte, NC 28273
United States

Polígono Industrial El Bayo, parcela I, 19
24492 Cubillos del Sil León
Spain

NEWS RELATED PRODUCTS

Trex Commercial Products
Diamon-Fusion International, Inc.
Diamon-Fusion International, Inc.
Diamon-Fusion International, Inc.

Add new comment