HORN® starts heat-up process of Frigoglass´ 300 tpd furnace

Date: 31 May 2021
Source: www.hornglass.com
www.hornglass.com
HORN® has started the furnace heat-up process at glass packaging supplier Frigoglass' 300 t/d end fired furnace GF2 in Nigeria.

The heat-up started on Friday, 21 May. The first glass is expected on 2 June. The new container glass furnace manufactures glass in green and amber. The entire start-up process is and will further be supported by HORN® technicians. The project will be finished by mid of June 2021.



We would like to thank Frigoglass´ management and for the support of Mr Jagdish Agarwal as well as the management team in the execution of this fast project during the COVID-19 pandemic.