Engineering company finds Harmon tower construction defects 'pervasive'

Date: 18 July 2011
Source: http://www.lvrj.com/
The unfinished Harmon tower at CityCenter is virtually unrepairable and could collapse in a "code-level" earthquake, according to a structural engineer hired by MGM Resorts International who examined the 27-story building.

In the report, members of Weidlinger Associates of Marina Del Rey, Calif., said they ran several tests on the building and found missing or misplaced reinforcing steel in columns, beams, shear walls and transfer walls throughout the tower below the 21st floor.



"The construction defects in the tower observed to date are so pervasive and varied in character that it is not possible to quickly implement a temporary or permanent repair to remediate the defects, or even determine whether such repairs can be performed," Chuckwuma Ekwueme, an associate principal with Weidlinger told CityCenter Vice President of Facility Operations William Ham in a letter dated Monday.



Read the full story

See more news about: